# L&T wins order for three battery storage projects totalling 6 GWh in the Middle East

> L&T's Renewables business will develop three 4-hour battery storage projects, with grid interconnections, pooling substations and underground cables, for an unnamed client.

- Topic: Contract award
- Event date: 2026-08-25
- First published on EPC Feed: 2026-10-24T06:44:58.097Z
- Updated: 2026-10-24T06:44:58.097Z
- Companies: Larsen & Toubro
- Page: https://epcfeed.com/news/lt-middle-east-bess-three-projects


## Key facts

- Contractor: Larsen & Toubro, Renewables business
- Client: Not named (Middle East)
- Projects: Three battery energy storage projects
- Storage capacity: 6 GWh in total
- Duration per project: 4-hour battery energy storage system
- Scope: Grid interconnection, pooling substations, underground cables

L&T's Renewables business has won a major order to develop three battery energy storage system (BESS) projects for a client in the Middle East, according to a release dated 25 August 2026. The release does not name the client or the country.

The three projects will collectively provide 6 gigawatt-hours of storage capacity. Each project features a 4-hour battery energy storage system capable of storing and dispatching energy.

The scope also includes grid interconnections, pooling substations and underground cables. The release says the order positions L&T as a key EPC player in the fast-growing energy storage sector.

The release does not disclose the contract value or the schedule.

## Sources

1. [L&T Renewables Business Wins (Major\*) Order for Battery Energy Storage System in the Middle East](https://www.larsentoubro.com/pressreleases/2026/2026-08-25-lt-renewables-business-wins-major-order-for-battery-energy-storage-system-in-the-middle-east). Company release, Larsen & Toubro, Published 2026-08-25, Read 2026-10-23.