# Venture Global reports CP2 modules and tank-roof milestones

> The owner’s August results dated construction observations separately from its future LNG-production targets.

- By: EPC Feed
- Topic: Project and operations update
- Subjects: LNG, Construction
- Event date: 2026-08-11
- First published on EPC Feed: 2026-11-08T11:58:03.299Z
- Updated: 2026-11-08T11:58:03.299Z
- Companies: Venture Global
- Countries: United States
- Page: https://epcfeed.com/news/venture-global-cp2-construction-update-august-2026


## Key facts

- Project: CP2 LNG, Cameron Parish, Louisiana
- Construction observation date: 11 August 2026
- Base project first LNG: Targeted for the second half of 2027


Venture Global’s second-quarter results, published on 11 August 2026, reported 16 liquefaction modules on site at CP2, roofs raised on all four LNG tanks, and five gas and steam turbines on foundations. The developer targeted first LNG from CP2 in the second half of 2027.

These are owner-reported observations at the release date, rather than a current construction completion percentage. The same release separately targeted investment sanction for the proposed CP2 Expansion in early 2027 and first expansion production in late 2028, subject to regulatory approval.

## Project intelligence

- [CP2 LNG, Cameron Parish, Louisiana](https://epcfeed.com/companies/venture-global#project-1): Venture Global; Developer; project company Venture Global CP2 LNG, LLC



## Sources

1. [Venture Global second-quarter 2026 results](https://investors.ventureglobal.com/news/news-details/2026/Venture-Global-Reports-Second-Quarter-2026-Results/default.aspx). Company release, Venture Global, Published 2026-08-11, Read 2026-11-08.