TenderRenewables and storage

Ukrhydroenergo tenders battery storage at four of its hydropower plants

Four lots of 46, 66, 60 and 25 MW are open to electronic bids until 12 November 2026.

Generated illustration for this story, not a photograph of the project.

Ukrhydroenergo (UHE) has invited bids for the design, supply and installation of battery energy storage systems with energy management systems at four hydropower plants, in a procurement published by the World Bank on 16 September 2026.

  • Lot 1: Kyiv HPP/PSP, 46 MW
  • Lot 2: Kaniv HPP, 66 MW
  • Lot 3: Kremenchuk HPP, 60 MW
  • Lot 4: Seredniodniprovska HPP, 25 MW

Bidders may bid for any number of lots, and the contracts include training for UHE staff. Bids are submitted through the electronic procurement system by 16:00 Kyiv time on 12 November 2026, with a bid-securing declaration instead of a bid security. The notice lists an IBRD loan (9284-UA) and loans and a grant from the CTF as financing.

Sources

  1. World Bank procurement notice OP00468997: Request for Bids, battery energy storage at four hydropower plantsOfficial noticeWorld BankPublished 16 September 2026Read 23 October 2026

Spotted an error or have a primary source we should read? Send a correction.