Ukrhydroenergo tenders battery storage at four of its hydropower plants
Four lots of 46, 66, 60 and 25 MW are open to electronic bids until 12 November 2026.
- Event
- First published on EPC Feed
- Sources
- 1 listed below
- Reading time
- 1 min
Ukrhydroenergo (UHE) has invited bids for the design, supply and installation of battery energy storage systems with energy management systems at four hydropower plants, in a procurement published by the World Bank on 16 September 2026.
- Lot 1: Kyiv HPP/PSP, 46 MW
- Lot 2: Kaniv HPP, 66 MW
- Lot 3: Kremenchuk HPP, 60 MW
- Lot 4: Seredniodniprovska HPP, 25 MW
Bidders may bid for any number of lots, and the contracts include training for UHE staff. Bids are submitted through the electronic procurement system by 16:00 Kyiv time on 12 November 2026, with a bid-securing declaration instead of a bid security. The notice lists an IBRD loan (9284-UA) and loans and a grant from the CTF as financing.
Sources
Spotted an error or have a primary source we should read? Send a correction.