CP2 owner reports 24 of 36 modules on site and targets first LNG in mid-2027
The November update separates base-project deliveries from the proposed 10 mtpa expansion and its pending investment decision.
- Event
- First published on EPC Feed
- Sources
- 3 listed below
- Reading time
- 2 min

Venture Global reported 24 of the base CP2 project’s 36 liquefaction modules on site in results released on 10 November 2026. The owner narrowed its first-LNG forecast to mid-year 2027 and reported that much of the gas-pretreatment and power equipment was also on site. The disclosure is a dated delivery observation and production target; it does not provide an overall construction-completion percentage or establish commercial operations.
The same release describes the separate CP2 brownfield expansion as 10 mtpa, with FID targeted in early 2027 and first production in late 2028. Those expansion forecasts remain distinct from the base project’s mid-2027 target. A module count cannot establish that all systems have been installed, integrated, tested or commissioned. Nor does the expansion capacity description itself establish a new regulatory authorisation.
DOE/HGEO Order No. 5521, dated 9 November, now grants export authority for the expansion to qualifying FTA destinations, equivalent to 620.5 Bcf/year of natural gas for 20 years from first commercial export, with a three-year make-up period. The expansion’s non-FTA request is not decided by this order. Its application description gives approximately 11.7 mtpa at peak output, whereas the owner’s 10 November release uses 10 mtpa. Those stated bases remain separate; neither number is silently substituted for the other. Export authority also does not replace a FERC facility decision or establish an expansion FID.
Worley announced a reimbursable EPC contract for the expansion on 4 November, after early engineering under a Master Services Agreement. Its announcement identifies existing EPC services for CP2 Phase 1 and Phase 2. That contract award and the owner’s later reporting are separate events: the November results do not disclose a new EPC price or convert the expansion’s investment target into an achieved decision.
The owner also reports a $3.0 billion, 364-day revolving facility at Venture Global LNG, Inc. for general corporate purposes, including certain CP2 and Plaquemines expansion costs. This is a corporate financing arrangement, not a disclosed price for Worley’s expansion contract or evidence that every expansion cost is funded. EPC Feed retains the base development and proposed expansion as separate canonical scopes, with their own sourced roles, observations and targets.